Adobe Workfront Practice Exam 2025 – Comprehensive Test Prep

Question: 1 / 400

What should not be done when creating a project template according to Adobe Workfront best practices?

Include task durations, planned hours, and predecessors

Attach custom forms to the project template

The correct approach when creating a project template involves several best practices that enhance the effectiveness and efficiency of project management. Including task durations, planned hours, and predecessors is essential because it helps in setting realistic timelines and dependencies for tasks, which are critical for project planning. Assigning tasks to job roles rather than individual users allows for greater flexibility and easier resource management, as roles can be filled by different team members depending on availability and skill set.

Reviewing project templates regularly is also vital to ensure they remain relevant and effective over time, taking into account lessons learned from past projects and any changes in process or organizational objectives.

While attaching custom forms can be beneficial in capturing additional specific data or requirements, it is not a core necessity for creating an effective project template. In some scenarios, custom forms may complicate the template or be less applicable for broad use across different projects, making it less of a priority compared to the other practices mentioned. Thus, best practices focus more on streamlining and standardizing project templates to facilitate usability, rather than customizing them excessively.

Get further explanation with Examzify DeepDiveBeta

Assign tasks to job roles instead of individual users

Review project templates regularly